Punjab Newsline, Chandigarh, April 4 —
The 31st Board Meeting of the HRIDC was held here today under the chairmanship of CS Anurag Rastogi to review the status of priority railway infrastructure projects in the state.
Key decisions and updates were shared regarding the commissioning of important sections, including the Manesar-Patli line, Kurukshetra Elevated Track, and the proposed Eastern Orbital Rail Corridor. ACS, B&R, Anurag Agarwal was also present in the meeting. The Chief Secretary emphasized the need for timely completion and coordination among stakeholders to ensure efficient implementation of the infrastructure projects aimed at boosting connectivity and economic growth in Haryana.
It was informed that the CRS, Northern Circle, has granted sanction for the remodeling of Patli Yard in connection with the commissioning of the Patli-Manesar (Priority Section). The critical interconnection of the Haryana Orbital Rail Corridor (HORC) with the Indian Railways network at Patli was completed on March 28, 2025.
The MSIL Railway Yard, including formation, track, overhead electrification (OHE), and signaling and telecommunication (S&T) works, has been completed.